**********
[NOTICE: The Go Solar at Home Project is now completed. Information that follows on this page is provided for background and reference. See our home page for any updated projects information.]
**********
Information Meetings
General Information about Rooftop Solar
**********
[NOTICE: The Solarize Plano Projects are now completed. Information that follows on this page related to these projects is included for background and reference for other groups considering a solarize project. For an overall summary of the completion of the projects, see Solarize Project Summaries.]
**********
2014 Solarize Plano Project (PROJECT COMPLETED)
Project Communications
- Sept 15, 2014 - Solarize Plano Project Communications Update
- July 22, 2014 - Solarize Plano Project - 1 Day remaining for Decision Point 2
- July 16, 2014 - Enrollment Now Closed - but "to-do" list items remain
- July 12, 2014 - Solarize Plano Project Communications Update - Only 3 days remaining!
- July 7, 2014 - Solarize Plano Project - Special Status Email - Key Next Steps
- July 1, 2014 - Solarize Plano Project Communications Update
- June 20, 2014 - Solarize Plano Project Communications Update
- June 10, 2014 - Solarize Plano Project Communications Update
- May 25, 2014 - Solarize Plano Project Communications - Phase 1 Contracting complete!
- May 16, 2014 - Solarize Plano Project Communications - Phase 2 Announcement
- May 6, 2014 - Solarize Plano Project Communications Update
- May 1, 2014 - Solarize Plano Project Communications Update
- April 23, 2014 - Solarize Plano Project Communications Update
- April 1, 2014 - Solarize Plano Project Communications Update - Think Solar BEFORE summer electric bills
- March 18, 2014 - 2014 Solarize Plano Project Communications Update
- March 7, 2014 - 2014 Solarize Plano Project Communications Update
- March 3, 2014 - Status Update - RFP Issued, RFP Review Team Members Needed
- RFP Review Team Questionnaire (see this status update for additional details)
- February 21, 2014 - 2014 Solarize Plano Project Communications Update
- February 7, 2014 - 2014 Solarize Plano Project Communications Update
Information Meetings
- Schedules and Presentations - On-demand information sessions are now available
Enrollee Decision Process
- Participant Decision Points - Solarize Plano Project enrollees will have three main decision points and decisions to make during the project timeline. Please review this document to obtain an understanding of these decisions and the corresponding timeline.
2013 Solarize Plano Project - COMPLETED
(Historical information)
Project Communications
- May 16, 2014 - Solarbration! - Final Status Update
- February 21, 2014 - Installation Timeline Status Update
- January 30, 2014 - Installation Timeline Status Update
- December 13, 2013 - Installation Timeline Status Update
- November 26, 2013 - Installation Timeline Status Update
- November 6, 2013 - 2nd enrollment period - Upcoming Milestone Dates
- October 29, 2013 - Installation Timeline Status Update
- September 27, 2013 - Revised Installation Timeline
- August 28, 2013 - Solarize Plano Project Contract Status and Pricing Tiers
- August 16, 2013 - Let the PV Solar Installations Begin!
- August 9, 2013 - Project Status Update
- August 1, 2013 - Decision Point 2 Response Needed by August 5th
- July 26, 2013 - Project Status Update
- July 18, 2013 - Homework Assignment
- June 27, 2013 - First information meeting summary
- Schedules and Presentations - On-demand information sessions are now available
- Participant Decision Points - Solarize Plano Project enrollees will have three main decision points and decisions to make during the project timeline. Please review this document to obtain an understanding of these decisions and the corresponding timeline.
Net Metering
- Net Metering considerations in North Texas, also see blog article - The "Real" Power to Choose!
- Additional Information on Distributed Generation and Net Metering
- Re-opened September 27, 2013 through October 31, 2013 (*** now closed ***)
- For details, go to http://www.solarizeplano.org/ and follow the six steps described there.
- Number of site assessments completed - 52 total
- Number and size of proposals submitted to enrollees - 49 total, 235.7 kW total
- Number and size of contracts committed by enrollees - 25 total, 120.8 kW total
- **** Enrollment closed as of end of the day August 5, 2013 ***** The interest and participation has greatly exceeded expectations. The final total number of persons completing the signup form was over 200.
- To learn more about the project
and to enroll, go to http://www.solarizeplano.org/